Sunday, December 14, 2014

NDA cabinet earlier this week, passed big changes to the Electricity Act

The Narendra Modi government has been criticised in the last few months for not going about with reforms as enthusiastically as hoped but, in one sector, at least, expect major changes. Continuing an initiative held over from the previous regime, the NDA cabinet earlier this week, passed big changes to the Electricity Act, the main law which governs the economics of the sector.

If passed by Parliament, consumers could get the choice to buy power from companies of their choice rather than being tied to a single provider as is the case in most states. At the same time though, this could accelerate a process by which state utilities' losses deepen, imposing a heavy fiscal burden on their parent governments.

Experts that ET Magazine spoke to had mixed reactions about the changes. Surya P Sethi, a former principal advisor on power to earlier governments, hailed the reforms as 'essential for competition'. While arguing that the Act had been poorly implemented so far, he said: "I am glad this is being done now. Better late than never." Others were more circumspect.

Says Ashwini Chitnis, a senior research associate at Prayas Energy Group, a non-profit organisation looking at energy sector policy issues. "The amendments aim at making fundamental changes to the sector structure and organisation, but it is not clear how these changes will help in tackling issues such as state utility losses, rising tariffs, fuel availability problems, and poor quality of service ."

Moving Reforms Along 

In the first set of reforms starting in the mid-90s, a major aim was to split existing power companies into separate parts, each focused on generating power, transmitting it, or distributing it to the end consumer. This enabled distribution companies to buy power in the open market, from generators across the country, rather than from companies owned by the state of which they were a part.

"What possibly the government wants to do is actually take that one step forward. What the reforms aim to do is replicate this freedom for the end consumer as well," says Sushanta K Chatterjee, head of regulatory affairs at the Central Electricity Regulatory Commission (CERC), the apex regulator for the power sector.

Even in the current regime, the socalled open access is allowed for larger consumers with a load of 1 MW and above. A factory in Gurgaon for instance can, in theory, at least, buy power from any provider in the country, or even from a short-term power market such as IEX at a lower rate, rather than from the default distributor which, in most cases, is owned by the state government.

But open access never really took off for one simple reason: the biggest loser in this deal — the default distributor — was also the one that controlled the wires leading to the customer. The company that controlled the pipes was entitled to a surcharge for allowing its infrastructure to be used to supply power — and while the surcharge was regulated, it was often set very high, making any open access deal financially unviable. While power sector regulators in each state were in theory independent and could set such surcharges at a level that was competitive, in many cases they did not and were heavily under the influence of the state government, which also happened to be the parent of the distribution company in question.

But even apart from the surcharges, the state government had effective control over the transmission infrastructure within the state boundaries and could simply block any flow of power to an open access buyer from the seller. "A big problem was that the state-owned incumbent blocked access to market to competitors — through influence over the network operator as also state regulators imposing very high cross-subsidy surcharge and additional surcharge on open access — both being owned by the state government," says Amit Kapur, partner with J Sagar Associates, a law firm.
What the new reforms aim to do is to take the physical wire network and move that into a separate company for a given region or area (say, south Delhi or north Mumbai). Within a given area, multiple distribution companies would be licenced to operate and offer power to consumers, with all of them having the right to supply power to a given consumer, while paying a set, common fee to the company which now owns the wires.

By separating 'carriage' and 'content' this way, the Act aims to level the playing field between an existing supplier in any area who also happens to own the pipes, and challengers who want to enter with cheaper costs and power contracts but are hampered from doing so because of the costs of building an entire network. Your local distribution company will then be only responsible for billing you for the power you used, and collecting money.

Will it Work? 

Customers in Mumbai are already allowed to choose between competing suppliers such as Tata and Reliance, and the experience has hardly been trouble-free. There has been litigation around the issue and while some disputes have been resolved by the Supreme Court, others remain. Even supporters of the reforms are guarded in their assessment of how successful the latest reforms will be.

"The details of how this reform will be carried out are crucial," says Chatterjee. And while such details need not necessarily be covered in the letter of the Act itself, they remain key to the success of the reforms. One key issue is how the transition is carried out. Take the Maharashtra State Electricity Distribution Company (MSEDCL), for instance, which supplies power across Maharashtra excluding Mumbai. As Chitnis points out, MSEDCL has a range of power supply contracts with various types of power generation companies, with some of its contracts such as those based on hydropower being extremely cheap. With such sources of cheaper power, MSEDCL is able to mitigate the costs of supplying cheaper power to agricultural consumers. If new suppliers do come in, the key question is what happens to those cheaper contracts that MSEDCL has.
Given that it will just be one among a number of suppliers, it will hardly need all that power that it has contracted to buy from generation companies. If those power contracts are to be reallocated to new discoms, will the cheaper power that MSEDCL has, be included as well? The bigger problem is one of new entrants looking to cherry-pick the best consumers from the incumbent. If this does happen, the incumbent state utility will be left with poorer, less lucrative consumers, while at the same time losing high-paying consumers to competing (and possibly more efficient) private sector utilities.
And if, as in the case of MSEDCL, its cheapest sources of power are partly reallocated to the new entrants, it faces a double whammy — watching its average revenue from customers drop (as high-paying customers leave), and see its average cost of power purchase rise, as cheaper fuel sources are allocated to new entrants.

Sunday, November 30, 2014

Company plans to expand the capacity of its Mundra project by 1,500 MW by adding two units

Tata Power may cut dependence on Indonesian coal and explore other geographies to source the fuel for expansion of its 4,000 MW Mundra ultra mega power project in Gujarat.

The company owns stake in KPC mining company in Indonesia which owns and operates coal blocks in the island nation.

"It (import) could be from any market globally because after the HBA price regime was implemented in Indonesia, we get no advantage at all from ownership," Tata Power Managing Director Anil Sardana told PTI.

He said the coal for Mundra project expansion can be sourced from any other country and any other mine because one gets it at the market-determined price.

HBA price of Indonesia is the monthly coal reference rate which is calculated on the monthly average of four international coal indices.

"The expansion was on the assumption that the units will be linked to market phenomenon and we would be using imported coal," Sardana said.

The company plans to expand the capacity of its Mundra project by 1,500 MW by adding two units.

As per the original plan layout prepared by the Central Electricity Authority (CEA) there is space for space for two additional units.

"Since water is there, evacuation is there, every other facility is there and it makes sense for one to generate electricity at a cheaper price," Sardana said, adding that where else can one expect imported coal-based power being generated at less than Rs 3.

On whether the company would go ahead with the proposed expansion of the Mundra despite little clarity on the issue of compensatory tariff, Sardana said, "The compensatory tariff issue is only concerned with UMPP. As far as the two additional units are concerned, they will be at market prices, so therefore the two phases are completely different."

Central Electricity Regulatory Commission earlier this year asked the power procurers to pay Rs 329.45 crore as compensatory tariff for the Mundra plant to partly offset escalation in the price of imported coal.

Read More

Tuesday, November 25, 2014

India spends crore on power theft clampdown

India is going to great lengths to crack down on rampant electricity theft that has long plagued its power sector, with plans to spend ₹25,354 crore to deploy metering in cities and upgrade its old distribution networks, the Ministry of Power said on Thursday.

The "Integrated Power Development Scheme" will help reduce technical and commercial losses, as well as improve collection efficiency. The earmarked funds from the government will be offset from the total estimated cost of ₹32,612 crore.

Many Indians have come to view cheap, even free, power as a right rather than a privilege. Poor political will to address the thefts, and ageing transmission lines have badly hurt local distribution companies, with as much as 40 per cent of electricity going unpaid for in several states.

Addressing power theft to reduce losses forms part of Prime Minister Narendra Modi's key policy platform to bring uninterrupted power to the entire country. Modi was previously credited with tackling power shortages during his time as chief minister of Gujarat, curbing power theft and repairing the finances of distribution companies hit hard by unpaid bills.

The Union Cabinet chaired by the Prime Minister, Shri Narendra Modi, gave its approval to launch the scheme. State discoms and power departments will award the contracts for the execution of projects, which are scheduled to be completed within 24 months from date of award.

Read Source

Monday, November 17, 2014

Cyclone-prone Andhra Pradesh to switch over to underground power cabling

Cyclone-prone Andhra Pradesh is likely to become the first state in the country to supply electricity through underground cable system.

The massive changeover from the conventional pole system to underground cabling has been made possible due to a loan of Rs 716 crore granted by the Asian Development Bank, World Bank and Japan Bank.

Under the ambitious plan, a separate power supply line will be laid across 10 coastal districts at an estimated cost of Rs 838 crore.

Of this, the loan provided by ADB, WB and Japan Bank would account for Rs 716 crore at a nominal interest rate.

Read full article

Tuesday, October 7, 2014

India may pass China as biggest coal importer

As coal block deallocation looms, Glencore, the biggest trader of fuel, sees India imports rising to 180 mt in 2015 and then to 300 mt by 2020.

With deallocation ofcoal blocks putting a question mark on India's ability to meet any significant part of country's energy need, the country could soon overtake China as the world's biggest consumer of imported coal, global analysts including Glencore, one of world's largest trader of coal, predict.

Even as India gears up to import more coal as deallocated blocks are to be taken away from the private developers, China is faced with slowdown in energy consumption coupled with tighter regulations reducing import of low-grade polluting grades of coal.

"Amid weaker Chinese steel demand and lower domestic freight costs, we expect China's import needs to decline, eliminating what had been a key source of growth for the market. We expect global seaborne demand growth to slow considerably, with India the main source of incremental demand going forward," Daniel Rohr, analyst with Morningstar said in a report on Monday.

Glencore of US, producer and marketer of a host of commodities and a major force in global coal market, recently made presentation to analysts on coal that said "India has emerged as the dominant growth market".
In its presentation last week, Glencore said India's coal imports are expected to grow from 170 million tonne (mt) to 180 mt in 2015 and then to 300 mt by 2020.

"While that forecast is at the bullish end of market forecasts, few believe India's heavily regulated mining sector will be able to dig up enough coal to satisfy local demand. India could overtake China next year if only standard grades of thermal coal – bituminous and sub bituminous types – are counted," Commodities Note said on Monday.

India is currently the third-biggest thermal coal importer in the world.

If all kinds of grades are included, India would trail China's total imports of 220 mt in 2014, analysts said.

Glencore's figures are based on assumptions that India's coal-fired power capacity would go up from 145 gigawatt installed now to a target of 214 gigawatt by 2020, leading to 345 mt of fresh demand for coal.
The analysts have also noted current low level of stock of coal lying with the power plants indicating higher imports in coming days.

Country's Central Electricity Authority recently said coal stocks at 56 thermal plants have less than 7 days of fuel stock.

Of the 56 stations, 33 had less than four days of stock, CEA noted.

But rise in Indian imports wouldn't be able to compensate likely drop in Chinese imports as a result of which global trade will fall.

Glencore said global coal imports in 2014 would drop to 308 mt from 312 mt in 2013 but would again rise to 317 mt in 2015 And this would adversely impact global prices.

Read more

Energiser for Bihar power

India Power Corporation Ltd (IPCL) is looking to invest Rs 33 crore to beef up its distribution network in Bihar.

In June, the Calcutta-based power company’s wholly owned subsidiary — India Power Corporation (Bodhgaya) Ltd — had entered into an agreement with South Bihar Power Distribution Company Ltd to supply power for 15 years to Gaya, Bodhgaya and Manpur areas of Bihar.

“We have submitted an investment plan of Rs 33 crore to upgrade infrastructure and induct new power distribution technology to the Bihar Electricity Regulatory Commission and are awaiting a formal approval before we implement the capital expenditure programme,” IPCL chairman Hemant Kanoria said.

“Our focus is on the industrial requirement for which the distribution capacity is being scaled up. This will be followed up by certain changes in the network to ensure quality of power supply,” Kanoria said.

According to the company, the investment will help to address issues such as obsolete equipment, overloading and poor reliability.

Kanoria said the management had identified core areas that would require investment to ensure quality service. The company can cater to over 1 lakh customers in Gaya and adjoining areas.

It is too early for IPCL to track any change in power demand or make future projections. However, aggregate power consumption has gone up with the increase in hours of supply after the company took charge of the distribution.

Read more

Monday, October 6, 2014

PFC to appoint consultants for monitoring projects

State-run Power Finance Corporation is looking for consultants for monitoring the ongoing electricity generation and transmission stations and for facilitating the removal of bottlenecks in project completion.

A Power Project Monitoring Panel has been set up through the Power Project Progress Assessment Society to monitor the progress of power projects so as to commission them on time.

There is requirement of Power Project Monitoring Consultants in the area of coal availability and logistics, an official circular said.

The consultants will be appointed on a contract for a period of two years.

“The contract can be terminated on either side without assigning any reason with one month’s notice,” the circular said.

The applicant should not be more than 64 years of age on the date of appointment.

The primary function of the consultants will be to handle issues related to coal supply for power projects under development and in operation including any other facet considered critical.

Consultants will also have the responsibility of facilitating the identification of bottlenecks and suggest remedial measures for the requirement, it said.

For this purpose, the consultant would be needed to interact in his assigned area of function with State governments, ministries of the central government, financing institutions, regulatory agencies and other agencies involved with project implementation.

PFC is engaged in providing funds for various power projects in generation, transmission, and distribution sectors.

Source: www.the Hindu business line.com

Read more

Tuesday, September 30, 2014

Cameron calls for coal phase out.

UK Prime Minister David Cameron has called for existing coal-fired power plants in the UK to be phased out in the next 10 to 15 years in a tweet following his speech at the UN climate summit in New York. His words come despite concerns in the industry that coal is still needed to play a vital role in energy generation and supply.

Cameron’s tweet, posted by the UK Mission to the United Nations, read: ’We’ve said no to new coal [without] carbon capture and storage and plan to phase out existing coal over next 10-15 years.’
While not stated explicitly in his speech at the climate summit, the UK team at the UN in New York said on the Twitter social media site afterwards that the UK government intends to phase out existing coal stations, with new coal-fired power stations to use carbon capture and storage technology.

This is the first time that a phasing out measure has been announced in the UK, though European Union rules on pollutants from coal-fired power stations state that older coal-fired plants will have to be fitted with clean technology sooner rather than later.

In contrast to the prime minister’s stance, UK energy companies such as EDF Energy have expressed that coal-fired power stations are critical to “bridging the energy gap between now and when the company can deliver new low-carbon generating capacity” and that switching away from coal too quickly could lead to higher carbon generation.

’If the UK were to close all its existing coal stations in the next few years, it is possible that they could be replaced by new gas-fired stations,’ EDF Energy says on its website. ’While the carbon footprint of new gas-fired generating plant would be smaller than the existing coal-fired power stations, they could still be substantial. Early replacement could therefore lock the UK into higher carbon generation for the lifetime of the new fossil-fuelled plants.’

EDF said it believes that the UK should use a “diverse range of fuels” including nuclear, renewable energy sources, and as the government proposes, coal and gas fitted with CCS technology, to ensure the long-term security of electricity supply in the UK.

Interestingly, the Guardian previously reported in August this year that the UK government was requesting that one of Europe’s most polluting coal power stations should stay open, despite its nitrogen oxide emissions exceeding new legal limits by five times.

The Aberthaw power plant in South Wales was said to be in the top 30 highest carbon-emitting plants in Europe by the Climate Action Network and alliance of non-governmental organisations in the “Europe’s Dirty 30” report.

Following Cameron’s announcement on Twitter, green campaigner Greenpeace UK called for both the Conservative and Labour politicians to announce a clear end date for polluting coal plants. 

This article originally appeared on www.cleanenergypipeline.coma clean energy news service operated by VB Research, a sister publication to The Engineer

Source

Wednesday, September 24, 2014

Shortage of electricity, Power plants-Shut down

From: The editor, Business Today. DT.: 24-09-2014

At the time of going to press, news was coming in that Prime Minister Narendra Modi would launch his ambitious "Make in India" campaign next week. Companies from across the globe have been invited for the function, and many have indicated they would attend. At the function, the Prime Minister is likely to announce major incentives to make India an attractive destination for setting up manufacturing plants for even global companies. A number of manufacturing hubs are expected to be created because of this programme, bringing in investments, creating hundreds of thousands of jobs, and giving a boost to the economy.

One of the crucial things that can make or break this programme is the availability of power. Reliable, inexpensive and uninterrupted power is an absolute must for a manufacturing unit to function smoothly. (There are others, of course, like tax incentives, land availability for expansion and peaceful labour, but even after all those are in place, manufacturers need to be assured of good power supply.)

The problem is that currently a number of thermal power plants in the country have shut down because they have run out of coal - and there are others which are in a precarious situation because they have just one or two days of stocks left as buffer. Almost one-third of the power capacity in the country is not generating any electricity due to fuel supply problems. Thus, unless the problem of domestic coal production and supplies is fixed - and fixed very quickly - Modi's dreams of making India a global manufacturing hub cannot come true.

The irony is that India has over 300 billion tonnes of fuel as reserves, and this is enough to fulfil our needs for the next 200 years. The issue is that we have been producing less than 600 million tonnes a year of coal from domestic mines, though we need a minimum of one billion tonnes per annum immediately.

Unless the coal crisis is sorted out, the Prime Minister's Make in India campaign will come to nought. And even the economic recovery currently under way could come under strain.

- - Read more..

Tuesday, September 16, 2014

L&T Construction Wins Orders Valued Rs 2050 crore

Mumbai, Sept 15 (IBNS): The construction arm of L&T has won new orders worth Rs 2050 crores across various business segments in Aug and Sept 2014.

The Power Transmission & Distribution business of L & T has bagged international and domestic orders worth Rs 1213 crores.

Larsen & Toubro Saudi Arabia LLC, a fully owned subsidiary of L&T, has bagged a major international order from the National Grid, Saudi Arabia (a subsidiary of Saudi Electricity Company) for the construction of an Extra High Voltage Double Circuit Transmission Line with a route length of 192 km.

This project will improve the power system reliability in Shedgum and Uthmaniyah areas in the eastern region of Saudi Arabia. Secured against stiff competition, L&T’s scope in this turnkey order involves design, engineering, testing and supply of EHV transmission towers, conductors, insulators, other transmission accessories, testing and commissioning of the line. The project is scheduled to be completed in 24 months.

On the domestic front, a turnkey order has been received from the Tamilnadu Transmission Corporation limited (TANTRANSCO) for establishing 400/230kV AIS & GIS substations at Karamadai near Coimbatore, Poiyur near Trichy and at Chennai Central.

Another order has been secured from the West Bengal State Electricity Distribution Company Limited. The Project involves supply, erection, testing and commissioning of 33/11 kV Medium Voltage substations as part of the Power Distribution Network for enhancing electricity infrastructure under the RAPDRP Scheme in major towns of West Bengal.

--Read more..